Permitting a New Home in Washtenaw County: What to Expect and How to Stay Ahead of It
Permitting is the part of new home construction that surprises people the most — not because the process is impossible to navigate, but because most homeowners go into it without a clear picture of how many agencies are involved, how their sequence depends on each other, and how much a single missed step can delay the entire project.
This post covers what the permitting and approvals process actually looks like for a new single-family home in Washtenaw County — including where the City of Ann Arbor, the townships, and the Chelsea Area Construction Agency each play a different role. If you’re in the planning stages of a new build, reading this before you break ground will save you real time and money.
First: Who Issues Your Permit Depends on Where You’re Building
This is the detail that catches most people off guard. Washtenaw County doesn’t administer building permits uniformly across its entire geography. Where you’re building determines which agency handles your permits and inspections — and the processes differ meaningfully.
The City of Ann Arbor runs its own Planning and Development Services division with its own Unified Development Code, setback standards, and permit review workflow. If you’re building inside city limits, you’re working with Ann Arbor’s Building and Rental Services department, not Washtenaw County.
Most Washtenaw County townships — including Pittsfield, Webster, Superior, and Ann Arbor Township — route permits through the Washtenaw County Building Inspection Department at 705 N. Zeeb Road. That department enforces Michigan’s State Construction Code and handles building, electrical, mechanical, and plumbing permits.
Chelsea, Dexter, Lima, Lyndon, Sharon Township, and Sylvan Township all use the Chelsea Area Construction Agency (CACA) — a shared services agency that issues and inspects all permits for those communities. If you’re building in any of those jurisdictions, CACA is your building permit authority, not the county.
Before you do anything else, confirm which jurisdiction your lot sits in and which agency handles permits there. Your general contractor should know this immediately — and if they don’t, that’s a signal worth paying attention to.
Layer One: Zoning Approval
Before a building permit can be issued, your project needs to clear zoning. Zoning determines what can be built on a given lot and under what conditions: how close the structure can sit to property lines (setbacks), how tall it can be, what percentage of the lot it can cover, and what the lot’s designated use allows.
For a standard new single-family home on a residentially zoned lot, zoning approval is typically straightforward — you’re building a permitted use, and the design meets dimensional standards. But there are situations that complicate this:
- Odd-shaped or undersized lots can trigger setback conflicts, particularly on infill lots in established neighborhoods. What looks buildable on a map sometimes isn’t, or requires a variance.
- Lots near the Huron River or wetlands may fall within FEMA-designated Special Flood Hazard Areas, which impose additional design and elevation requirements and can limit the buildable area of the lot.
- Lots with existing structures being torn down for new construction need to confirm that the new build’s footprint and design will conform to current zoning — what was grandfathered on the old structure doesn’t automatically carry over.
- Non-conforming lot conditions may require a variance hearing before the local Zoning Board of Appeals (ZBA). In Dexter, for example, ZBA meetings are held on a set monthly schedule — missing the submission deadline means waiting another cycle.
Zoning compliance should be verified before a lot purchase, not after. We’ve seen clients fall in love with a parcel only to discover after closing that the buildable area was far more constrained than the lot size implied.
Layer Two: Well and Septic Permits (Where Municipal Services Aren’t Available)
Much of what makes Washtenaw County attractive for new construction — the rural townships, the larger lots outside Ann Arbor, the properties in Dexter, Chelsea, and the surrounding area — is also territory that isn’t served by municipal water and sewer. That means well and septic permits, and those come from a different agency entirely.
Well and septic permits in Washtenaw County are issued by the Washtenaw County Environmental Health Division (734-222-3800), which operates separately from the Building Inspection Department. The process runs like this:
- Soil evaluation first. A licensed soil scientist evaluates the lot — test pits are dug, and soil texture, depth, drainage, and the seasonal high water table are all assessed. Washtenaw County requires this evaluation before a septic permit will be issued. You cannot skip or shortcut this step, and it needs to be scheduled in advance.
- System design and permit application. Based on the soil evaluation results, a licensed designer creates a septic system plan. The design must account for bedroom count (which drives tank sizing), drain field dimensions, and required setback distances from wells, property lines, and structures. The completed design is submitted to Environmental Health along with the application and fees (new installation permits typically run $200–$500 in Washtenaw County).
- Health department review. Environmental Health reviews the design for code compliance. The full permitting process — soil evaluation through permit issuance — generally takes 2 to 6 weeks depending on scheduling and whether revisions are needed.
- Inspection during and after installation. All excavations require inspection before backfilling. The system cannot be covered without inspection. Septic permits are valid for two years from issuance.
One important local note: in Sylvan Township and several other townships in the western part of the county, the Environmental Health Department’s well and septic approval is required before the township will issue a zoning permit. That sequence matters — a delay in the septic permit can hold up everything downstream.
FCG holds a Washtenaw County septic installation license, which means we can manage this piece of the process directly rather than coordinating a separate specialty contractor. On lots that need both septic and construction work sequenced tightly, that matters.
Layer Three: The Building Permit
Once zoning is cleared and — where applicable — the well and septic permit is in hand, the building permit application can move forward. For new single-family construction, this involves submitting:
- A complete set of construction drawings
- A site plan showing the structure’s footprint, setbacks, driveways, and utility connections
- Foundation and structural details
- Energy compliance documentation (Michigan enforces the Michigan Residential Code, which has specific insulation and energy efficiency requirements)
In Washtenaw County (unincorporated areas), the Building Inspection Department at 705 N. Zeeb Road handles plan review. Plans must be submitted and approved before permits are issued and before any construction can begin. Separate permits are required for the building itself and for mechanical, electrical, and plumbing systems — these are distinct permit applications, though they’re typically submitted together as a package.
For projects in CACA’s jurisdiction (Chelsea, Dexter, and the surrounding townships), the same permit types apply, but are administered through CACA rather than the county. Timelines and submission processes differ slightly between agencies.
One point worth flagging: Washtenaw County also has specific radon-resistant construction requirements. New homes are required to include radon-resistant construction features per the Michigan Residential Building Code, and inspectors will be looking for compliance.
Layer Four: Additional Permits Depending on Site Conditions
Depending on your lot, additional permits may be required before or during construction:
- Soil Erosion and Sedimentation Control permit. Required from Washtenaw County’s Water Resources Commissioner if you’re disturbing more than one acre of land, or if your project is within 500 feet of surface water — lakes, streams, drains, or wetlands — and disturbs 225 square feet or more. Most new home construction lots will need this.
- Drain Use permit. Any work that crosses, modifies, or discharges into a county drain — or involves work within a county drain easement — requires a separate permit from the Washtenaw County Water Resources Commissioner.
- Driveway Approach permit. A permit from the Washtenaw County Road Commission (555 N. Zeeb Road, 734-327-6642) is required for any new driveway that connects to a county road right-of-way.
- EGLE review. Any impacts to wetlands or water bodies may require a permit from the Michigan Department of Environment, Great Lakes, and Energy (EGLE). This is separate from and in addition to county-level review.
- MISS DIG notification. Before any excavation begins, Michigan law requires contractors to contact MISS DIG (dial 811) to have underground utilities located and marked. This isn’t a permit, but it’s a legal requirement and a critical safety step.
The Inspection Sequence During Construction
Pulling a permit isn’t a one-time event — it opens a series of required inspections that must pass at specific stages of construction before the next phase can proceed. The Washtenaw County Building Inspection Department enforces these sequenced checkpoints:
- Foundation inspection. Before concrete is poured, the footing excavation is inspected for depth, size, and positioning. In Michigan, footings must extend below the frost line (42 inches), so this is a non-negotiable step.
- Framing inspection. After rough framing is complete but before insulation and drywall go in — the structure needs to be open and visible for the inspector.
- Rough mechanical, plumbing, and electrical inspections. Each of these trades has its own inspection before walls are closed. The county enforces the 2015 Michigan Mechanical Code, the 2015 Michigan Plumbing Code, and the 2014 National Electrical Code with state amendments.
- Insulation inspection. Insulation is inspected before drywall is installed.
- Final inspection. The completed structure is inspected across all systems before a Certificate of Occupancy is issued. You cannot legally occupy the home without it.
Each inspection must be scheduled in advance. For Washtenaw County, inspection requests must be made the day prior to the requested inspection. If an inspector finds a deficiency, work stops until corrections are made and re-inspection is completed. A contractor who plans ahead and builds to code generally moves through inspections without issue. Problems arise when work gets ahead of inspection scheduling or when details are left to the last minute.
How Long Does This All Take?
There’s no single answer, but here’s a realistic picture for a new single-family home in Washtenaw County under normal conditions:
- Zoning review: 1–4 weeks for a straightforward application; longer if a variance is required (ZBA schedules run monthly).
- Soil evaluation and septic permit: 2–6 weeks from initial application to permit issuance.
- Building permit plan review: Varies by agency and season. Spring and summer bring heavier volume. Budget 4–8 weeks for plan review on a new home submission.
- Permitting total (pre-construction): On a well-prepared project with no complications, 8–16 weeks from first application to permit-in-hand is realistic. Complications — a variance hearing, a soil evaluation that requires redesign, plan review revisions — add time.
The agencies aren’t working against you, but they’re also not waiting for you. Submitting an incomplete application, missing a required document, or getting the sequencing wrong adds weeks that could have been avoided. A general contractor who’s done this in Washtenaw County before knows what each agency needs and when.
What FCG Manages So You Don’t Have To
We handle permitting as part of our project management scope — not as a favor, but because it’s part of building a house correctly. That means coordinating with the right agency for your lot’s jurisdiction, submitting complete applications the first time, sequencing the septic and building permit processes so one doesn’t hold up the other, scheduling inspections at the right stages, and staying current with any revision requests from plan review.
For lots in Washtenaw County that need septic, FCG’s own installation license means one fewer handoff — we’re not waiting on a subcontractor to get scheduled; we’re doing it ourselves and integrating it directly into the construction timeline.
If you’re planning a new home build in Ann Arbor, Dexter, Chelsea, Saline, Brighton, or anywhere in Southeast Michigan, the permitting conversation is worth having early — before you’ve committed to a lot or a timeline that doesn’t account for what approvals actually require.
Schedule a free consultation with FCG and let’s walk through what your specific project and location will need.
Your Trusted Southeast Michigan General Contractor
At Fletcher Contracting Group, we help homeowners across Ann Arbor, Dexter, Chelsea, Saline, and Brighton bring their architectural and design plans to life. From home additions and renovations to complete construction management, our team ensures every project is delivered on schedule, on budget, and with lasting quality.
Ready to expand your home’s possibilities?
Schedule a free consultation today to discuss your second-story addition in Southeast Michigan.
Fletcher Contracting Group — You bring the plans. We’ll build it right.
“I rarely leave reviews, but working with Jerome was a truly great experience. With the advent of remote work, I needed a dedicated office space. He identified open space in the garage that if converted into a partial second story, would save money on building an entirely new structure. It’d also maintain the design integrity of my home. I now have a private workspace with a 1/2 bath that’s far better than expected. Overall, he & his team were responsive, helpful & results-oriented. Call Jerome. He’s one of the few who still care.” – H.B., Dexter
“Went from a terribly outdated bathroom with a single sink and CARPET to a tiled jack & jill with a modern, clean aesthetic. Jerome suggested opening a wall for a doorway & now my 2 growing sons have their own entrance from their bedrooms. So practical – and so much less bickering. Thanks Jerome. You guys are fantastic!” – Janie A., Ann Arbor